Karachi Electric Supply Company (KESC) and Aga Khan Hospital and Medical College Foundation (AKHMCF) have signed contract agreements with Siemens Pakistan for establishment of a 132KV GIS Grid Station at AKHMCF premises, at a total cost of Rs 680.7 million.
The Grid Station would be jointly shared by KESC and AKHMCF. At the contract signing, KESC was represented by Syed Arshad Masood Zahidi, Chief Generation and Transmission Officer, while AKHMCF was represented by Karim Nur Mohamed, Director General Planning and Development. The new Grid Station would allow reliable supply of electricity to AKHMCF, given the vital nature of its healthcare services to the patients, in addition to KESC consumers.
via Siemens to set up 132KV Grid at Aga Khan Hospital | Business Recorder.